Foreign project - FAT factory undergoing testing
For FAT Factory Acceptance Test, as a part of the ISO file system, the factory test documents are generally conducted according to the IEC standard factory test items, including special requirements for customer requirements, particularly strengthening the secondary system function inspection.

Standard format files generally include the following content:
Scope Scope The Mandatory Routine tests (refer clause 7 of IEC 62271-1 and IEC 62271-200) are as follows
The mandatory routine tests are as follows (refer to Chapter 7 of IEC 62271-1 and IEC 62271-200) Preparation before Test
Prepare EHS requirements before testing
safety requirements
List of inspection Item, standard and testing equipment
List of testing items, standards, and testing equipment
FAT test procedure FAT
Dielectric test on the main circuit
Measurement of the resistance of the main circuit through dielectric testing
Design and visual checks for measuring the resistance of the main circuit
Mechanical operation tests for design and appearance inspection
Mechanical operation testing Tests on Auxiliary and control circuits & Test of auxiliary electrical devices(interlocks)
Auxiliary and control circuit testing and auxiliary electrical device testing (lockout) Bus bar inspection
Busbar inspection Protection level inspection
Protection level inspection
Foreign projects will pay attention to the performance parameters of components, such as the mechanical performance of circuit breakers, opening and closing time, as well as the phase sequence, inflection point voltage, and other parameters of current transformers and voltage transformers. The parameters will be verified through a current injection test, and the system function will be verified, such as the parameter setting verification of microcomputer protection devices and the accuracy of actions.

There are also requirements for surface spraying, thickness, color difference, copper bar material inspection, conductivity measurement, and silver plating thickness measurement. These require spot checks and confirmation of incoming inspection reports. If inconsistencies are found, more items may need to be inspected, which may affect integrity.
FAT Test report FAT
The test report FAT report is officially archived and retained by the customer.
It is recommended that the manufacturer first complete the testing and verification of key factory projects on their own, such as power frequency withstand voltage, appearance inspection (surface spraying, label identification), circuit breaker rocking in and out, grounding switch operation and interlocking verification, to ensure that everything is foolproof and avoid problems in front of customers, which may affect the company's image in production management, quality control and other aspects, causing a lack of trust and inability to obtain subsequent projects.
~END
Recently Posted
-
Transformer Factory Tests: Routine, Type and Special Tests Explained
August 28, 2026An importer once accepted a transformer shipment without reading the test report, only to find the unit failed on site because its
Read More -
UL891 distribution panel
August 28, 2026Switchgear and separately separated distribution panels require a rear channel for connecting incoming and outgoing feeder cables.
Read More -
Oil-Immersed Transformers for Solar PV Power Plants
August 27, 2026A solar developer once watched a new plant lose several weeks of generation because the transformer feeding the grid connection fa
Read More -
Dry-Type vs Oil-Immersed Transformer: How to Choose
August 26, 2026A facilities engineer once had to shut down a hospital wing because the transformer serving it leaked oil onto the floor below. Th
Read More